A. Shikaripalya Lake Restoration

(Funded by Samsung Semiconductor India Research)

Project Duration: 2021-2023 (3 phases)

Key Interventions:

  • Removed 14,344 cu.m sludge + 43,312 cu.m silt
  • Created natural sewage treatment wetlands
  • Built 2.8 km walking path
  • Planted 1,800 native trees

Quantifiable Results:
🔹 Water holding capacity increased by 30.7 crore liters
🔹 150+ borewells recharged
🔹 500+ daily visitors

Challenges Overcome:

  • Heavy rainfall disrupting earthwork
  • 15ft deep sludge layers
  • Plastic waste removal (32 tons extracted)

B. Hunsmaranahalli Lake Project

(Supported by Lowe’s India)

Transformational Changes:

  • Desilted 22-acre lakebed (+2.35 lakh liter capacity)
  • 7 new silt-trapping inlets installed
  • 2,000 saplings planted (forestry + ornamental)
  • Community washroom constructed